QUANTITY OF SHUTTERING MATERIALS REQUIRED AT A TIME
Shuttering Sheets              – 3200 nos
Props                                 – 4900 nos
Adjustable span                 – 1100 nos
Plywood (8’ X 4’) -              - 800 nos
Wooden shuttering materials

LABOUR STRENGTH REQUIRED AT PEAK TIME;
Form workers      - 50 nos
Bar benders        - 30 nos
Masons               - 90 nos
Unskilled labour  - 120 nos

DETAILS OF TECHNICAL & ADMINSTRATIVE PERSONNEL TO BE EMPLOYED FOR THE WORK
Project Engineer                      – 1 no
Assistant Project Engineer       – 2 nos
Quantity Surveyors                  – 2 nos
Site Supervisors                       – 4 nos
Safety Officer                           – 1 no

 
 